DETAILS:
Planned Traffic: 9 mil pax/year
Client: SPEA Engineering S.p.A.
Service: Detailed design of the new northern apron
Value of works: €10 million
Reference code: ICAO Code C
Year: 2018
TASK:
GESAC, the management company at Capodichino, wanted to expand the southern side of Taxiway A, and Air Alliance was appointed to carry out the detailed design of the new northern apron that would follow from it. The work covers a fully equipped four-stand Code C apron complete with pavement, storm water drainage and electrical network, together with four service roads — two of which give access to a new helicopter apron forming part of a separate project. Upgraded Code C infrastructure on entirely new pavements secures a long period of trouble-free growth for Naples.
Focus
- Analysis of the aeronautical obstacle survey
- Topographic survey of the whole area and the existing facilities
- Apron layout with obstacle analysis
- Rigid and flexible apron pavement design for the expected traffic volumes and mix
- Design of four service roads, two of them serving a new helicopter apron
- Grading of the taxiway strip
- Storm water drainage network, with runoff calculation and channels tapped into the existing system
- Horizontal markings, AGL, vertical signs and systems
- LED AGL primary and secondary electrical network, with monitoring and substations
- PCA system, 400 Hz aircraft supply and aircraft refuelling pits