Rome Fiumicino – ULD stocking area (2016)
15 February 2016
DETAILS:
Airport traffic: 2.4 mil pax/year
Client: Alveare Consortium, for ADP S.p.A.
Service: Pre-detailed design — phase two of the complete airfield upgrade
Value of works: €12.5 million (whole programme)
Reference code: ICAO Code C, D and E
Year: 2017
TASK:
The second phase of the Brindisi airfield upgrade, taking the scheme from preliminary to pre-detailed design and into full compliance with current EASA regulations across both runways, the taxiway system and the aprons. It added a comprehensive HWD survey to measure elastic moduli and residual life, and took the design down to pavement structures calculated in FAARFIELD, new profiles and sections, holding positions set to ICAO standards, and a complete EASA airport certification checklist. The Runway 13-31 thresholds were relocated to clear the obstacle limitation surfaces.
Focus
- HWD pavement survey for elastic moduli and residual life
- Aeronautical obstacle surveying
- Relocation of the Runway 13-31 thresholds to clear the obstacle limitation surfaces
- New runway declared distances
- Taxiway geometry for Code C, D and E compliance
- Runway, taxiway, shoulder and apron pavement design in FAARFIELD
- Drainage grading, new profiles and sections
- LED AGL system for runways and taxiways
- Horizontal markings, signs and aircraft holding positions to ICAO standards
- Extended approach path with related airside service roads
- New general aviation apron layout
- Construction phasing plan
- Complete EASA airport certification checklist